Nripendra Mishra, Chairman of Ram Temple Construction Committee
– Photo : amar ujala
Expansion
On the third day of the meeting of the Ram Temple Construction Committee, there was a brainstorming session on completing all the construction and beautification work in the Ramjanmabhoomi complex as per the scheduled time. Chairman of the committee, Nripendra Mishra said that 8.5 lakh cubic feet of Vanshipaharpur red stone is required in the wall of the temple. Work is being affected due to reduced number of workers. There are 200 workers less.
He said that the target of completing all the work by June 2025 does not seem to be achieved now. It will take three more months. Work is going on on all the projects. A place has been selected to keep the shoes and slippers of thousands of devotees, the construction of the building on it will be started this week.
Read this also – Chhath festival concluded with the offering of Arghya to the rising sun, women made wishes by plunging into water, photos
Read this also – Akhilesh Yadav remembered demonetization, said – this chapter will be written in black color
Weak stones on the first floor will be removed
On the first floor of the Ram temple located in Ramnagari Ayodhya, some stones have been installed whose thickness is less. The quality is also not good. It is being told that these are old stones. Now these stones will be removed and replaced with Makrana stones. This decision has been taken on the first day of the meeting of Ram Temple Construction Committee. Committee chairman Nripendra Mishra has disclosed this.
Told that the stones whose thickness is less will be replaced. He told that 80 murals based on Ramkatha are to be made in the 800 meter long parkota. All these murals are to be made on bronze. These will be pasted on the stones. Of these, 10 murals have been completed. A mural has also been installed.